1.0OPENING REMARKS AND PRAYER
1.1Bishop PZ Mukwena opened the meeting with a prayer and a reflection on the story of Noah as an engineer, drawing parallels to the current project.PM
2.0ADOPTION OF PREVIOUS MINUTES
2.1Decision: The previous minutes were reviewed and adopted without corrections.
3.0MATTERS ARISING FROM THE PREVIOUS MINUTES
3.1EIA Certificate Update
3.1.1The circulations for the EIA certificate are ongoing, with an expected completion by the third week of July.
3.1.2No objections have been raised during the circulations.
3.2Architectural Plans and Design Feedback
3.2.1Discussions were held on the architectural designs, including the layout and features of the Bongano project.
3.2.2Feedback was provided on the design elements, including the preference for modern finishes over face brick.PM, SM and JBM
3.2.3The need for clear dimensions and sectional titles for the office suites was emphasized.PM
3.3Power Needs and ZESA Approval
3.3.1The ZESA power approval process is ongoing, with a grid assessment being conducted.
3.3.2The project may require upgrading local transformers or substations based on the assessment results.
3.4Compensation for Delays
3.4.1Clause 6 of the addendum specifies that the developer shall pay a delayed completion rental calculated at 80% of the open market rental of the property.KM
3.5Security Arrangements
3.5.1Security arrangements for the site were discussed, including the involvement of a neighborhood watch and a security company.KM

Action items

Reference numbers are assigned when this draft is submitted.

Final Remarks

RefDescriptionAction
4.0CLOSING REMARKS AND BENEDICTION
4.1Bishop PZ Mukwena concluded the meeting with a prayer, emphasizing the importance of divine guidance in the project's success.PM